Original practice · fully worked
Original variant: conditional charge for a delayed sterilization cycle
A sterilization cycle has an exponential duration with mean 5 hours. At hour 4 the cycle is still running. A maintenance agreement charges 20 credits if the cycle finishes by hour 7 and 80 credits if it finishes after hour 7. Calculate the conditional expected charge.
- A
9.024 - B
34.796 - C
43.905 - D
47.071 - E
52.929
Answer and calculation
Memorylessness makes the chance of running beyond hour 7 equal to exp(-3/5)=0.548812 after the observation at hour 4. Weighting the 20- and 80-credit charges gives 52.928698, so choice E.
Setup
Setup
Let R be the residual duration after the cycle is observed running at hour four.
R=T−4∣T>4 Model
Model
By memorylessness, the residual is exponential with the original five-hour mean.
Pr(R>3)=e−3/5=0.5488116361… Pr(R≤3)=1−e−3/5=0.4511883639… Compute
Compute
Weight the two possible agreement charges by the conditional completion cases.
E[C∣T>4]=20(1−e−3/5)+80e−3/5 =52.92869817… Answer
Answer
The conditional expected charge is approximately 52.929 credits.
52.929(E)